Sixteen More Points, Still Eight of 101

A new benchmark called SWE-CoWork went up on arXiv on 15 November, from a group listed as TokenWave AI. It puts a coding agent into an assignment that is already under way at a simulated software company. The agent gets a short onboarding note, a frozen repository, and a workplace with project boards, versioned documents, chat history, merge requests and CI records. It also gets 26 colleagues, each an LLM-backed character with a defined role, limited knowledge and rules about when they will share it. The requirements are spread across those records and those people. The agent has to find them, build the change, and write a handoff note.

The headline sentence of the abstract: “The two leading models satisfy approximately 63% of fail-to-pass (F2P) tests but complete fewer than 8% of assignments.” The sentence after it is the one I spent the most time on: “Providing complete requirements upfront improves F2P by approximately 16 percentage points for Seed Evolving and GPT-6 Astra, yet leaves complete task success unchanged.”

I think the benchmark is well built and worth having. The “unchanged” in that second sentence says less than it seems to, though, and the reason is in how the two scores are made.

Two scores from the same tests

Each of the 101 tasks comes with a fixed set of executable tests. Fail-to-pass (F2P) tests check new behavior the assignment asks for. Pass-to-pass (P2P) tests check that existing behavior still works. Across the benchmark there are 2,699 F2P test nodes and 562 P2P nodes, and the median task has 32 nodes in total.

The paper reports three numbers. F2P and P2P are pooled: passed nodes divided by total nodes across all tasks, so tasks with more tests carry more weight (the paper says this itself). Pass rate is “the proportion of tasks for which every F2P and P2P test node passes in the same run.” One failed node out of 60 counts the same as 60 out of 60.

Claude Opus 5.5 passes 63.84 percent of F2P nodes and completes 6.93 percent of tasks. GPT-6 Astra passes 62.91 percent and completes 7.92 percent. None of the other nine models gets above 39.09 percent F2P or 0.99 percent pass rate. With 101 tasks, those pass rates are 7, 8 and 1 tasks.

Then comes the Oracle-Spec experiment. The same two models run the same 101 tasks with the same repositories, tests, scaffold and eight-hour budget, but the complete requirement set is handed over at the start and there are no colleagues to consult. Table 3 of the paper:

F2P and pass rate with and without complete requirements Horizontal bars from Table 3 of the SWE-CoWork paper (arXiv 2611.20218, November 2026), on a 0 to 100 percent scale. Seed Evolving: F2P 39.09 percent in the CoWork setting and 55.76 percent with the complete specification; pass rate 0.99 percent in both. GPT-6 Astra: F2P 62.91 percent in CoWork and 78.84 percent with the specification; pass rate 7.92 percent in both. The F2P bars grow by about 16 points for each model and the pass-rate bars do not change. CO-WORK VS ORACLE-SPEC · 101 TASKS · TABLE 3, SWE-COWORK, NOV 2026 Seed Evolving GPT-6 Astra F2P, colleagues F2P, full spec Pass rate, colleagues Pass rate, full spec F2P, colleagues F2P, full spec Pass rate, colleagues Pass rate, full spec 39.09% F2P, Seed Evolving, CoWork — SWE-CoWork Table 3, Nov 2026 55.76% F2P, Seed Evolving, Oracle-Spec — SWE-CoWork Table 3, Nov 2026 0.99% pass rate, Seed Evolving, CoWork — SWE-CoWork Table 3, Nov 2026 0.99% pass rate, Seed Evolving, Oracle-Spec — SWE-CoWork Table 3, Nov 2026 62.91% F2P, GPT-6 Astra, CoWork — SWE-CoWork Table 3, Nov 2026 78.84% F2P, GPT-6 Astra, Oracle-Spec — SWE-CoWork Table 3, Nov 2026 7.92% pass rate, GPT-6 Astra, CoWork — SWE-CoWork Table 3, Nov 2026 7.92% pass rate, GPT-6 Astra, Oracle-Spec — SWE-CoWork Table 3, Nov 2026 39.09 55.76 (+16.67) 0.99 0.99 (+0.00) 62.91 78.84 (+15.93) 7.92 7.92 (+0.00) Percent of F2P test nodes passed (pooled), and percent of tasks with every F2P and P2P node passing. One run per task.
The full specification lifts both models' test scores by about 16 points. Neither model finishes a single extra task.

The paper reads it this way: “These remaining failures occur during implementation and verification, after requirements are available.” That is probably part of it. The result also fits a simpler explanation that has nothing to do with agents, and the paper doesn’t rule it out.

What a cut at 100 percent throws away

Pass rate is a continuous score cut into two categories at its most extreme point. Each task has a fraction of nodes passing, anywhere from 0 to 1, and pass rate asks only whether that fraction equals 1.

Statisticians have been measuring what this costs for decades. In 1983 Jacob Cohen worked through the case of a normally distributed variable split at its mean and found the loss in statistical power was “equivalent to discarding 38% and 60% of the cases” when one or both variables were split. He then added: “As dichotomization departs from the mean, the costs in variance accounted for and in power are even larger.” Fedorov, Mannino and Zhang put a floor on the information loss for a normal outcome: at least 1 − 2/π, about 36 percent, so that “100 continuous observations are statistically equivalent to 158 dichotomized observations,” and the loss grows as the cut point moves away from its optimum. Ragland showed in epidemiology that the size of the effect you see and the power you have both depend on where the cut sits, and that a statement about association “has limited meaning unless both the cutpoint and the distribution of the outcome variable are specified.”

None of those papers studied software tests, and per-task pass fractions are not normal. They pile up near the ends. The general point still carries over. A cut at the very end of the scale is the worst place to detect change. A task that rises from 40 percent of its nodes passing to 95 percent shows up in F2P and is invisible to pass rate. About 0.1593 × 2,699 ≈ 430 more F2P nodes passed for GPT-6 Astra with the full specification. If those gains land in tasks that were already partly done and still fall short of every node, pass rate stays at 8. That is what you would expect from this metric even if requirements matter a lot.

Some quick arithmetic shows how far the outcome is from independent coin flips per node. If each of a median task’s 32 nodes passed independently at 63 percent, the chance of all 32 passing would be about 0.63³² ≈ 4 in 10 million. Seven or eight of 101 tasks passing means failures cluster heavily: a few tasks get very close and most don’t. Under that kind of distribution, the full specification can help the near-misses climb without getting them over the line.

Eight of 101 cannot show “unchanged”

The second problem is sample size. As far as the paper describes, each model ran each task once. It refers to “101 Claude-Opus-5.5 CoWork trajectories,” and I found no repeated runs, seeds or confidence intervals for pass rate. With n = 101, “unchanged” is a statement about integers: 8 tasks before, 8 after. The paper also doesn’t say whether they are the same eight tasks.

Pass rates with 95 percent intervals on 101 single runs Point estimates and Wilson 95 percent intervals for the pass rates in the SWE-CoWork paper, computed from task counts out of 101. GPT-6 Astra: 8 of 101, 7.92 percent, interval 4.1 to 14.9 percent, in both the colleague and full-specification settings. Claude Opus 5.5: 7 of 101, 6.93 percent, interval 3.4 to 13.6 percent. Seed Evolving: 1 of 101, 0.99 percent, interval 0.2 to 5.4 percent, in both settings. The intervals for GPT-6 Astra span roughly 11 percentage points, wider than any change pass rate could plausibly register. PASS RATE · WILSON 95% INTERVAL · COUNTS FROM SWE-COWORK TABLES 2–3 0% 5% 10% 15% 20% GPT-6 Astra, colleagues GPT-6 Astra, full spec Claude Opus 5.5 Seed Evolving, colleagues Seed Evolving, full spec 8/101 = 7.92%, interval 4.1–14.9% — SWE-CoWork Table 2, Nov 2026; interval computed 8/101 = 7.92%, interval 4.1–14.9% — SWE-CoWork Table 3, Nov 2026; interval computed 7/101 = 6.93%, interval 3.4–13.6% — SWE-CoWork Table 2, Nov 2026; interval computed 1/101 = 0.99%, interval 0.2–5.4% — SWE-CoWork Table 2, Nov 2026; interval computed 1/101 = 0.99%, interval 0.2–5.4% — SWE-CoWork Table 3, Nov 2026; interval computed 8 · 4.1–14.9 8 · 4.1–14.9 7 · 3.4–13.6 1 · 0.2–5.4 1 · 0.2–5.4 Tasks passed of 101, then Wilson 95% interval in percent (my calculation from the paper's counts). Single run per task.
GPT-6 Astra's eight passes are consistent with a true rate anywhere from about 4 to 15 percent. A paired comparison on this sample could not register a few extra tasks either way.

From the paper’s counts, the Wilson 95 percent interval for 8 of 101 runs from about 4.1 to 14.9 percent. If the full specification really raised the completion rate by three or four points, a single run of 101 tasks would often still come back with eight, or seven, or nine. With one run per task, F2P is the only one of the paper’s three scores that can show a difference of the size the paper reports.

So when the paper says supplying requirements “leaves complete task success unchanged,” what it measured is that pass rate on one run of 101 tasks didn’t move, and on this sample it couldn’t have moved much. The F2P result is the informative one, and it says requirements matter: about 16 points for both models.

The handoff note is the better finding

The part of the paper I’d show to anyone deploying these agents is the requirement-level trace of Claude Opus 5.5’s 101 runs.

Opus sent its first question to the accountable owner for a mean of 93 percent of the cards it asked about. It still obtained only 64 percent of the 2,176 requirements held by colleagues. Most of the missing ones were with people it had already talked to: 17 percent of requirements were never raised with owners the agent had contacted about other cards, and only 3 percent belonged to owners it never contacted. Of 450 threads where a colleague deferred an answer, 153 got no follow-up at all. At the moment of deferral those threads had a median of 7.1 hours of budget left.

Then the handoff. “Among 826 requirements reported as completed at handoff, 255 (31%) fail their corresponding tests.” In one task the agent declared the assignment complete while its own notes still listed 8 pending requirements.

Thirty-one percent needs something to compare against. Figure 8a of the paper splits all 2,399 tested requirements by what the handoff said about them, so I can ask how much the note tells a reader who has to decide what to check.

How often a requirement passes its tests, by what the handoff said Share of requirements whose tests pass, for Claude Opus 5.5 across 2,399 tested requirements in SWE-CoWork, grouped by the agent's final handoff note. Reported done: 571 of 826 pass, 69 percent. Flagged as open: about 61 percent pass. Not mentioned: about 54 percent pass. All requirements: 1,477 of 2,399 pass, 62 percent. A requirement the agent called done is only seven points more likely to pass than a requirement picked at random, and one it flagged as still open passes about as often as average. CLAUDE OPUS 5.5 · 2,399 TESTED REQUIREMENTS · FIGURE 8A, SWE-COWORK, NOV 2026 Reported done Flagged open Not mentioned All requirements 69.1% pass (571 of 826) — SWE-CoWork Figure 8a and Section 6.3.4, Nov 2026 about 61% pass — from SWE-CoWork Figure 8a percentages, Nov 2026 about 54% pass — from SWE-CoWork Figure 8a percentages, Nov 2026 61.6% pass (1,477 of 2,399) — SWE-CoWork Figure 8a, Nov 2026 69% (571 / 826) ≈61% ≈54% 62% (1,477 / 2,399) 100% Open and not-mentioned rates derived from the figure's rounded shares (34/35% and 27/37%) of 1,477 passing and 922 failing. Dashed line: base rate across all tested requirements.
"Done" moves the odds from 62 percent to 69. "Still open" barely moves them at all. As a guide to what to check, the handoff note is close to noise.

Software project management studied this exact problem in people long before agents. Snow and Keil modeled the gap between true and reported project status in two stages: errors in what the manager perceives, then bias in what the manager chooses to report. In a later survey of project managers, Snow, Keil and Wallace found that “status reports were biased 60% of the time and that the bias was twice as likely to be optimistic as pessimistic.” Abdel-Hamid’s simulation of a NASA project traced the “90% syndrome,” where work sits at nearly done for a long time, to two causes interacting: underestimation, and “imprecise measurement of project progress due to poor visibility.”

The two numbers measure different things. A 60 percent rate of biased reports is about project-level traffic lights, and 31 percent is about requirement-level claims checked against hidden tests. But the two-stage split is useful here. The agent’s tests are private, so its sense of what is “done” rests on its own checks, which is the perception stage. The task where it declared completion with 8 items still pending in its own notes looks like the reporting stage. I can’t tell from the paper how the 255 split between the two. It matters because the fixes differ: better self-testing helps with the first, and only an outside check catches the second.

What I’d want before trusting the “unchanged” number

The benchmark builds something the field lacked: requirements spread across people and records, with an executable contract under every one of them. The requirement-level trace is the strongest part of the paper, and the F2P gap between models is large enough to survive a single run. What I’d add before anyone repeats “complete requirements don’t help task completion”:

The paper’s own summary, that “reliable delivery requires maintaining the state of individual requirements,” is probably right. I’d just base that on the requirement-level data, which is strong, and not on a pass rate that held at eight of 101.

References

  1. Lei X, Liu M, Zhu R, et al. (TokenWave AI). “SWE-CoWork: Benchmarking Coding Agents as Digital Employees in Organizations.” arXiv:2611.20218 [cs.SE], posted 15 November 2026. Tables 2–3, Figures 7–8, Sections 3.4, 5.1–5.2 and 6.3. arxiv.org/abs/2611.20218
  2. Cohen J. “The Cost of Dichotomization.” Applied Psychological Measurement 7(3):249–253, June 1983. doi:10.1177/014662168300700301
  3. Fedorov V, Mannino F, Zhang R. “Consequences of dichotomization.” Pharmaceutical Statistics 8(1):50–61, 2009 (online 3 April 2008). doi:10.1002/pst.331
  4. Ragland DR. “Dichotomizing Continuous Outcome Variables: Dependence of the Magnitude of Association and Statistical Power on the Cutpoint.” Epidemiology 3(5):434–440, September 1992. doi:10.1097/00001648-199209000-00009
  5. Snow AP, Keil M. “The challenge of accurate software project status reporting: a two-stage model incorporating status errors and reporting bias.” IEEE Transactions on Engineering Management 49(4):491–504, November 2002. doi:10.1109/TEM.2002.807290
  6. Snow AP, Keil M, Wallace L. “The effects of optimistic and pessimistic biasing on software project status reporting.” Information & Management 44(2):130–141, March 2007. doi:10.1016/j.im.2006.10.009
  7. Abdel-Hamid TK. “Understanding the ‘90% syndrome’ in software project management: A simulation-based case study.” Journal of Systems and Software 8(4):319–330, September 1988. doi:10.1016/0164-1212(88)90015-5